In every construction project, unexpected challenges remain an integral part of the field reality, even with the most meticulous studies and planning. One of the most critical of these challenges is the occurrence of Differential Settlement in the soil beneath a building's foundations. This can lead to structural cracks and an imbalance in load distribution, ultimately threatening the structure's integrity.
In this article, we share a real-world experience our consulting team faced in a commercial and administrative building project and how we addressed it with precise scientific steps and effective engineering solutions.
Project Description and Site Conditions
The project involved a commercial and administrative building consisting of a basement, ground floor, and 5 repetitive floors, with a total covered area exceeding 6,000 square meters. The project is located in a bustling urban area, and the site soil is mixed with layers of clay and sand-silt, with a fluctuating groundwater table at a depth of approximately 4.5 meters.
Problem Discovery
After completing the structural frame up to the second floor, our consulting team observed:
- The appearance of hairline cracks in some vertical walls.
- A slight tilt in the slab level next to one of the columns.
Upon precise measurement, a differential settlement of 1.8 cm was found in this specific column compared to the others. Although this figure may seem relatively small, differential settlement is far more dangerous than total settlement because it causes cracks and separations within the structure, affecting the building's performance and safety.
Engineering Analysis of the Cause
The office formed an emergency technical committee, which began with the following steps:
- Reviewing the original soil report, including the number and locations of boreholes.
- Performing an additional borehole next to the affected column.
- Reviewing the casting and construction sequence around the column.
We concluded that the cause was:
- The presence of a localized pocket of weak clay soil that was not detected in the original boreholes due to their spacing.
- Relatively rapid loading (casting two consecutive floors in a short period) increased the rate of immediate settlement.
Risk Assessment
Analysis of the results indicated that the potential remaining settlement could reach an additional 0.5–0.8 cm in the future. With the continuation of construction, this could lead to:
- Larger structural cracks.
- Deformation of adjacent slabs and columns.
- Weakening of the building's long-term stability.
Proposed Solutions
After an in-depth study, the team presented three main solutions, along with an analysis of each's advantages and disadvantages:
- Grouting:
- Solution: Injecting the soil beneath the column with a high-viscosity cement grout to increase soil density and fill voids.
- Pros and Cons: Relatively fast, lower cost, but its effectiveness is limited in dense clay soil as it does not allow the grout material to spread easily.
- Foundation Underpinning Using Micropiles:
- Solution: Installing 4 micropiles, 20 cm in diameter and 12 m long, next to the column's foundation and connecting them with a concrete pile cap to transfer the load to deeper, more bearing layers.
- Pros and Cons: A long-term and very safe solution, but it is more costly and requires specialized equipment and additional time.
- Temporary Column Lifting Using Hydraulic Jacks:
- Solution: Temporarily offloading the column, slightly lifting it, and then pouring a new leveling concrete layer.
- Pros and Cons: Quickly restores the level, but it is very complex, requires highly precise supervision, and does not address the root cause of the settlement
How to Choose the Most Suitable Solution
The choice of solution always depends on the results of additional boreholes, soil type, magnitude of settlement, and the building's age.
- Grouting is more effective in sandy or mixed sand-silt soils and less effective in clay.
- The Micropiles solution is ideal if the goal is to transfer the load to deeper layers without recasting or removing the structure.
- Temporary lifting is only used with limited settlement and under very strict engineering supervision.
Implementation of the Chosen Solution
The second solution (Micropiles) was chosen as the safest, most effective, and long-term option.
- Four micropiles, 20 cm in diameter and 12 m long, were installed.
- They were connected to the column base with a concrete pile cap.
- Construction work resumed with precise settlement monitoring using modern surveying equipment (Total Station).
Result: The additional settlement almost stopped (less than 0.2 cm), and the concrete structure became fully stable.
Lessons Learned
- The importance of increasing the number of boreholes during the soil report preparation and reducing the spacing between them, especially in heterogeneous soil.
- Accurate monitoring of settlement throughout the construction phases using modern equipment.
- Preparing proactive technical emergency plans for unexpected situations.
Conclusion
Civil engineering is not just about adhering to plans and numbers; it is the art of dealing with unexpected variables through bold scientific decisions and well-thought-out solutions. A minor differential settlement could have turned into a catastrophe, but thanks to scientific thinking and deep engineering analysis, it transformed into a success for the team, proving that genuine consulting expertise makes a difference.